Prerequisite(s): A change order must have been created but not yet submitted.
-or-
The awarded contractor must have sent the change order back for modification.
1. From your homepage, click the Contract Name link in the Contract Name column of the Contract List.
2. Hover your mouse over the Contract Management link on the menu bar.
3. Click the Manage Work Orders sub-link from the menu bar.
4. Click the Change Order Name link for the change order you wish to edit.
5. Refer to the CREATING A CHANGE ORDER for adding additional comments and making edits to the Change Order Name, Description, Change Order Effective and End Dates, Liquidated Damages, Incentives and/or line items.