Prerequisite(s): The Initial Base Work Order has been created for a Contract you have been
awarded.
A submittal package has been created.
1. From your homepage, click the Contract Name link in the Contract Name column of the Contract List.
2. Hover your mouse over the Contract Management link on the menu bar.
3. Click the Issues & Information Management sub-link from the menu bar.
4. Click View Log link associated with Submittal Package.
5. Click the submittal package link for the submittal package you wish to view or update.
6. Update the fields as appropriate.
7. Click the Save button.
Note: You may review each submittal associated with the package by click the submittal link at the bottom of the submittal package page. To remove a submittal from the package, you must return to the individual submittal (in edit mode) and change the Submittal Package field selection.